Funding fiasco report out soon
Reporter: Karen Doherty
Date published: 10 February 2010
Oldham Council cabinet
THE investigation into the Chadderton Wellbeing Centre funding fiasco should be completed within a fortnight.
An internal council audit was ordered after a massive blunder was revealed just days before the Wellington Street building opened in November.
The ruling Liberal Democrats say that the £100,000 running costs for the pool, fitness suite, library and meeting rooms were calculated and approved when Labour was running the council.
But it was then discovered that the true figure was £811,000 — more than eight times the amount.
However, Labour councillors are demanding an apology, saying that a trawl though official papers proves they did budget for the full amount.
Councillor Dave Hibbert, Labour’s only cabinet member, hit out at the time the investigation had taken.
He said: “I am surprised this report has taken so long because I found out this information within a week.”
Most Viewed News Stories
- 1Tributes paid following death of hugely respected Oldham community figure Dale Harris
- 2You can score free tickets to a Latics game while supporting Dr Kershaw’s Hospice
- 3Primary school in Uppermill considers introducing new ‘faith-based’ entry criteria to tackle...
- 4Public inquiry announced into rail upgrade that could leave villages ‘cut off’ for months
- 5Trio arrested, drugs and weapons seized following Chadderton raid